Written summary, conclusion of the contract and the standstill period

What happens after the evaluation of tenders: requesting certificates, sending and correcting the written summary, the standstill period and its exceptions, the role of the second-best tenderer and the conclusion of the contract.

Updated 17 November 2026Draft – awaiting legal review

Legal basisSection 69(6) · Section 79(1) · Section 79(2) · Section 79(4) · Section 79(5) · Section 80(5) · Section 131(1) · Section 131(4) · Section 131(5) · Section 131(6) · Section 131(7) · Section 131(8) · official text

The examination and evaluation of tenders end with the written summary of the evaluation of tenders (írásbeli összegezés): by sending it, the contracting authority informs the tenderers of the outcome of the procedure (Kbt. Section 79(2)), and the standstill period (szerződéskötési moratórium) runs from it (Kbt. Section 131(6)). This guide follows the steps in order, before and after the outcome is communicated: requesting certificates, sending and correcting the summary, the standstill period and its exceptions, the role of the second-best tenderer and the conclusion of the contract.

Before the decision closing the procedure: certificates

Before the decision, the contracting authority invites the tenderer ranked best under the award criteria, with a suitable time limit, to submit the certificates on exclusion grounds and selection criteria, and checks the databases that serve that purpose (Kbt. Section 69(4)). If that tenderer does not comply, the next best-ranked tenderer must be invited; only a tenderer that has met its obligation to provide certificates may be named the winner (Kbt. Section 69(5)).

The contracting authority may also invite one or more of the next tenderers in the ranking to submit certificates. It may name the second-best tenderer in the summary only if it invited that tenderer too before the decision and also checked the databases for its tender; and it may do this only where, given the evaluation method, disregarding a tender would not change the relative ranking of the others (Kbt. Section 69(6)). Where, in an open procedure, the examination follows the evaluation, the tender of the winner, and of the second-best tenderer the contracting authority wishes to name, must be examined in full, including the certificates, before the decision (Kbt. Section 81(5)).

The written summary

At the end of the assessment, the contracting authority prepares a written summary with the content set by legislation adopted under the Kbt.; where tenders could be submitted for lots, it may prepare it lot by lot (Kbt. Section 79(2)). Tenderers must be informed in writing of the outcome of the procedure, of the procedure being unsuccessful, of a tender being declared invalid and of an exclusion, with detailed reasons, as soon as possible after the decision and at the latest within three working days (Kbt. Section 79(1)); the contracting authority does this by sending the summary to all tenderers at the same time (Kbt. Section 79(2)).

Correction and amendment

The contracting authority may correct a clerical error in the summary (names swapped or misspelled, a numerical or calculation error), on request or of its own motion; it must send the corrected summary to all tenderers at the same time, at the latest within ten days of sending the outcome (Kbt. Section 79(5)).

If, after sending the outcome, the contracting authority finds that the outcome was unlawful, it may amend the summary until the twentieth day after it was sent, where the amendment remedies the infringement; where needed it may withdraw a notice of invalidity, and it may rescind a contract already concluded or, where the original position cannot be restored, terminate it with immediate effect. The amended summary must be sent to all tenderers at the same time, without delay (Kbt. Section 79(4)). Within the same time limit it may also carry out acts of examination or evaluation, to the extent needed to remedy the infringement (Kbt. Section 79(4a)). On a request for pre-litigation dispute resolution (előzetes vitarendezés), or on the finding of a body that funds or audits the procurement, it may amend even after that time limit, provided the contract has not yet been concluded (Kbt. Section 80(4), Kbt. Section 79(4b)).

The standstill period

The contract may not be concluded before the end of the ten-day period that follows the day the written summary is sent. If the summary is corrected and data on the success of the procedure, the validity of a tender or the result of the evaluation change, the ten days that follow the day the amended summary is sent apply. In a procedure under Section 115 the period is five days (Kbt. Section 131(6)). The rules on counting time limits apply to it: the day the period starts is not counted, and if the last day is not a working day, the period ends on the next working day (Kbt. Section 48(5), Kbt. Section 48(1), Kbt. Section 48(3)). The guide on time limits and the time limit calculator help with the count.

The binding period of the winning tender (ajánlati kötöttség), and of the second-best tenderer if the summary named it, is extended by thirty days, or sixty for works, counted from the day the summary is sent (Kbt. Section 131(5)); the contract must be concluded within that period (Kbt. Section 131(6)).

When the standstill period need not be waited out

The contract may be concluded before the ten-day or five-day period ends (Kbt. Section 131(8)):

  • where only one tender was submitted in an open procedure, in certain negotiated procedures without publication, in a single-stage concession award procedure or in a single-stage procedure under Section 117 (Kbt. Section 131(8)(a));
  • where only one tender was submitted in a multi-stage procedure and, if a request to participate was invalid or an exclusion took place, the time limit for a review of that decision has expired for those concerned, or the Public Procurement Arbitration Board (Közbeszerzési Döntőbizottság) has found it lawful (Kbt. Section 131(8)(b));
  • in a negotiated procedure without publication started for reasons of extreme urgency (Kbt. Section 131(8)(c));
  • for a purchase under a framework agreement or a dynamic purchasing system (Kbt. Section 131(8)(d));
  • in a negotiated procedure without publication started on certain grounds of Section 98, where the President of the Public Procurement Authority did not exercise, within the time limit open to them, the right to start review proceedings (Kbt. Section 131(8)(e));
  • where only one tender was submitted in a procedure under Section 115 (Kbt. Section 131(8)(f)).

Pre-litigation dispute resolution and review

A tenderer may challenge the written summary through pre-litigation dispute resolution within three working days of learning of the infringement (Kbt. Section 80(1)(a)). Where such a request was submitted in time and in due form about an act or document after the opening of tenders, the contract (where lots were possible, the contract for the lot concerned) may not be concluded from the submission of the request until ten days after the day the reply is sent, even if the standstill period would otherwise end earlier (Kbt. Section 80(5)); in a procedure under Section 115 this is five days (Kbt. Section 115(2)).

Where a request for review or an initiation of proceedings is lodged, the contract (where the procurement was divided into lots, the contract for the lot concerned) may not be concluded until a decision on the merits, or a decision ending the case, is taken, unless the Public Procurement Arbitration Board, or the court, permits it (Kbt. Section 156(4)). If the winner's binding period has expired in the meantime, the contract may be concluded with the winner if it declares that it maintains its tender (Kbt. Section 131(7)). A request for review of a decision closing the procedure may be lodged within ten days of learning of the infringement, or within five days in a procedure under Section 115 (Kbt. Section 148(3), Kbt. Section 148(4)); see the guide on remedies.

Concluding the contract

The contract must be concluded in writing with the winning tenderer (with the winning tenderers, for a joint tender), in line with the final conditions communicated in the procedure, the draft contract and the content of the tender; a successful procedure ends with the conclusion of the contract (Kbt. Section 131(1)). The contract must contain the evaluated elements of the winning tender (Kbt. Section 131(2)).

The contracting authority may conclude the contract only with the winner or, if the winner withdraws, with the next best-ranked tenderer, provided it named that tenderer in the summary (Kbt. Section 131(4)). The contracting authority and the winner are each released from the obligation to conclude the contract only where, because of a circumstance arising after the summary was sent, outside their control and unforeseeable, they would be unable to conclude or perform the contract, or rescission or termination would be justified (Kbt. Section 131(9)). Where a bid security (ajánlati biztosíték) was required and the conclusion of the contract fails for a reason within the tenderer's sphere, the security goes to the contracting authority (Kbt. Section 54(4)); where the contracting authority does not conclude the contract, it must make a payment to the winner and to the named second-best tenderer (Kbt. Section 54(6)(b)), in both cases except in the situation of Section 131(9).

If the standstill period is breached

The contract is null and void where the parties concluded it in breach of the standstill rules, thereby depriving the tenderer of the possibility of review before the contract was concluded, and at the same time breached the procurement rules in a way that affected the tenderer's chances of winning the procedure (Kbt. Section 137(1)(c)).

After the outcome

The contracting authority must send the notice on the outcome of the procedure for publication at the latest within twenty days of concluding the contract (Kbt. Section 37(2)). A tenderer may ask to inspect documents within five days of the summary being sent (Kbt. Section 45(1)), and a tenderer whose tender was valid may ask for separate information on the characteristics of the winning tender and its advantages over its own (Kbt. Section 45(2)).

In practice

  • It is good practice to calculate the last day of the standstill period from the day of sending, taking days that are not working days into account, and to fix the date for signing only then (Kbt. Section 48(3)).
  • A contracting authority that wishes to name the second-best tenderer must invite it to submit certificates before the decision: this cannot be done afterwards, and if the winner withdraws, the contract may be concluded only with a tenderer that was named (Kbt. Section 69(6), Kbt. Section 131(4)).
  • For tenderers the time limits are short: three working days for pre-litigation dispute resolution, ten days (five in a procedure under Section 115) for a request for review of the decision closing the procedure (Kbt. Section 80(1)(a), Kbt. Section 148(3), Kbt. Section 148(4)). Knowing the award criteria helps to check whether the scoring in the summary follows the notice.

Want your tender documents checked before publication? We will show you how Procurelex Ellenőrzés does it.

Request a demo

General information on the Kbt. in force. Not legal advice.