Modifying a public contract

When a public contract may be modified without a new procurement procedure under Section 141 of the Kbt., within which value and content limits, and what notice must be published.

Updated 17 November 2026Draft – awaiting legal review

Legal basisSection 141(2) · Section 141(3) · Section 141(4)(a) · Section 141(4)(b) · Section 141(4)(c) · Section 141(5) · Section 141(6) · Section 141(7) · Section 141(8) · Section 37(5) · Section 139(1) · Section 142(3) · official text

A contract concluded as the result of a procurement procedure cannot be modified at will: Section 141 of the Kbt. sets out the cases in which it may be modified without a new procurement procedure, and any other modification requires a new procedure (Kbt. Section 141(8)). This guide explains those grounds, the value and content limits that apply to them, when a modification is substantial, and what must be published about it.

What counts as a modification

Section 141 applies to a modification of the contract by the parties, or by one of them where entitled, and also where the parties' legal relationship changes under the contract's own provisions (Kbt. Section 141(1)). Exercising an option is one example. A change in the person of the contractor (the winning tenderer) is governed by Section 139, while changes to the other elements of the relationship fall under Section 141 (Kbt. Section 139(2)).

The grounds at a glance

GroundMain conditionValue limitNotice
Low-value modification (Kbt. Section 141(2))does not alter the overall nature of the contract and is consistent with the nature of the original contractthe price increase stays below 10% of the original value (15% for works) and, for an original contract at or above the EU threshold, below the EU thresholdrequired
Pre-set conditions, options (Kbt. Section 141(4)(a))the contract sets out the precise conditions and content of the change clearly, in a way all tenderers could know in advancenone, but the overall nature may not changenot required (Kbt. Section 141(7))
Additional purchases from the original contractor (Kbt. Section 141(4)(b))a change of contractor is not feasible for economic or technical reasons and would cause significant inconvenience or a multiplication of costs50% of the original value, cumulativelyrequired
Unforeseeable circumstances (Kbt. Section 141(4)(c))could not be foreseen with due diligence, and the overall nature does not change50% of the original value, per modification where the circumstances are unrelatedrequired
Non-substantial modification (Kbt. Section 141(6))does not lay down substantive conditions materially different from the original onesnonerequired

For a modification under subsection (2) the conditions of subsections (4) and (6) need not be examined, and for one under subsection (4) those of subsection (6) need not be (Kbt. Section 141(2), Kbt. Section 141(4)).

Low-value modification

The contract may be modified without a new procedure if the increase in the price, or for several modifications their total net value, stays below 10% of the original contract value for services, supplies and works or services concessions, and below 15% for works; for an original contract whose value reaches the EU threshold it must also stay below the EU threshold (Kbt. Section 141(2)(a), Kbt. Section 141(2)(b)). In addition, the modification must not alter the overall nature of the contract and must be consistent with the nature of the original contract (Kbt. Section 141(2)(b)).

This ground applies only to modifications that change the value; where a modification affects several elements of the relationship, only to the elements linked to the change in value (Kbt. Section 141(3)). Nor may it be used where the contracting authority launched the original procedure under rules that could not lawfully have been applied had it set the estimated value at the value after the modification (Kbt. Section 141(3)) – for example, where the modified value would have required the EU procedural regime.

Pre-set conditions and options

The contract may be modified, or may change, if the contract itself sets out clearly, in a way all tenderers could know in advance, the precise conditions and content of later changes to specified elements, including the exercise of an option; such clauses may not, however, provide for modifications that would alter the overall nature of the contract (Kbt. Section 141(4)(a)).

Where the contract provides in this way for the indexation of a price element, the original contract value for the purposes of subsection (2) and subsection (4)(b)–(c) is determined on the basis of the indexed contract price; for works and services concessions without an indexation clause, the indexed value may be calculated using the annual average of the inflation rate published by the Hungarian Central Statistical Office (Központi Statisztikai Hivatal) (Kbt. Section 141(5)). It is therefore good practice to set out expected changes – quantity options, price adjustment – precisely in the draft contract.

Additional purchases from the original contractor

Where additional works, services or supplies that were not included in the original contract are needed from the original contractor, the contract may be modified if a change of contractor is not feasible for economic or technical reasons, in particular because of interchangeability or interoperability with existing equipment, services or installations (Kbt. Section 141(4)(b)(ba)), and would cause the contracting authority significant inconvenience or a substantial multiplication of costs (Kbt. Section 141(4)(b)(bb)). Both conditions must be met. The increase in the price, or for several modifications their combined net value, may not exceed 50% of the original contract value (Kbt. Section 141(4)(b)(bb)).

Unforeseeable circumstances

The contract may also be modified where the need for the modification was brought about by circumstances that the contracting authority, acting with due diligence, could not foresee, the modification does not alter the overall nature of the contract, and the price increase does not exceed 50% of the original contract value (Kbt. Section 141(4)(c)(ca), Kbt. Section 141(4)(c)(cb), Kbt. Section 141(4)(c)(cc)). Where several successive modifications arise from separate, unrelated circumstances, the limit applies to the net value of each modification, but successive modifications may not aim to circumvent this rule (Kbt. Section 141(4)(c)(cc)).

When a modification is substantial

Outside the cases of subsections (2) and (4), the contract may be modified without a new procedure if the modification is not substantial. A modification is substantial if it lays down substantive conditions materially different from the original contract terms, and it is always substantial where (Kbt. Section 141(6)):

  • it introduces conditions which, had they been part of the original procedure, would have allowed other tenderers or candidates to take part or another tender to win (Kbt. Section 141(6)(a));
  • it changes the economic balance of the contract in favour of the winning tenderer (Kbt. Section 141(6)(b));
  • it extends the scope of the contract considerably, to a significant new element compared with the tenderer's original obligations (Kbt. Section 141(6)(c)).

A change of contractor

The person of the contractor may change in two cases only (Kbt. Section 139(1)):

  • under a clear contract clause meeting Section 141(4)(a), where the successor is a project company (projekttársaság) or, to secure performance, a legal person financing the performance or a legal person it designates (Kbt. Section 139(1)(a));
  • by succession following a transformation, merger, division or other dissolution with a successor, the transfer of a whole business line operating as an economic unit, or the transfer of the contract in insolvency proceedings against the original contractor, provided the successor is not subject to a ground for exclusion, meets the selection criteria applied in the procedure, and the succession does not aim to circumvent the Kbt. (Kbt. Section 139(1)(b)).

In every other case the contractor may change only as the result of a new procurement procedure (Kbt. Section 139(2)). Replacing subcontractors and experts is covered in the guide on subcontractors.

Prohibitions and consequences

  • Outside the cases of Section 141, the contract may be modified only as the result of a new procurement procedure; a modification made by unlawfully dispensing with a procurement procedure is null and void (Kbt. Section 141(8), Kbt. Section 137(1)(a)).
  • A modification is null and void if it aims to release the winning tenderer from a breach of contract for which it is liable and its consequences, or to have the contracting authority take over extra work costs or, without justification, other risks borne by the winning tenderer (Kbt. Section 142(3)).
  • It breaches the principles of the Act if the contracting authority does not enforce its claims for breach where performance departs from the contract to an extent that would be a substantial modification (Kbt. Section 142(2)(b)).

Where a substantial modification of the contract that would require a new procedure under Section 141 is absolutely necessary, the contracting authority may terminate the contract or withdraw from it under the Civil Code (Ptk.) (Kbt. Section 143(1)(a)).

Notice and publication

A notice of the modification must be published, with the content of the template set by separate legislation, except in the case of Section 141(4)(a) (Kbt. Section 141(7), Kbt. Section 37(1)(j)). The notice must be sent for publication no later than five working days after the modification (Kbt. Section 37(5)). Once the notice appears, the modification must be published without delay, through the electronic public procurement system (EKR), in CoRe, the public electronic contract register of the Public Procurement Authority (Közbeszerzési Hatóság), and in the EKR (Kbt. Section 43(1)(b)).

Monitoring and remedies

The Public Procurement Authority monitors the notices of contract modifications and checks the performance and modification of contracts in contract-monitoring proceedings (Kbt. Section 187(2)(j)). Where a modification is likely to breach the Kbt., the President of the Authority initiates ex officio proceedings before the Public Procurement Arbitration Board (Közbeszerzési Döntőbizottság) (Kbt. Section 153(1)(c)), and for a modification contrary to Section 142(3) the Authority brings an action for a declaration of its invalidity (Kbt. Section 175(1)).

A modification that breaches the Kbt. can also be challenged before the Board (Kbt. Section 145(3)); the infringement is then deemed to have come to the requester's knowledge on the thirtieth day after the notice of the modification was published (Kbt. Section 148(7)(e)). In these cases the Board decides within sixty days of the opening of the proceedings (Kbt. Section 164(3)). The guide on remedies sets out how a request proceeds.

It is good practice to record in writing, for every modification, the ground relied on and the facts behind it – for subsection (4)(c), for instance, why the circumstance could not be foreseen – so that the conditions can be shown to have been met later on.