Practical guide

Abnormally low prices and other disproportionate commitments

When a contracting authority must ask for an explanation of a price or cost that appears abnormally low, which explanations it may accept, and when the tender must be declared invalid (Section 72 of the Kbt.).

Updated 17 November 2026Draft – awaiting legal review

Legal basisSection 72(1) · Section 72(2) · Section 72(3) · Section 72(4) · Section 72(5) · Section 72(6) · Section 72(7) · Section 73(1)(e) · Section 73(1)(g) · Section 81(4) · official text

Where the price or cost in a tender appears abnormally low in relation to the subject-matter of the procurement, the contracting authority must ask the tenderer in writing for data and an explanation (Kbt. Section 72(1)), and decides on the validity of the tender after weighing the reply (Kbt. Section 72(3)). This guide explains when that examination starts, which explanations may be accepted, when the tender must be declared invalid, and how the same applies to other commitments in the tender besides the price.

When an explanation must be requested

The request is mandatory where a tender appears abnormally low in relation to the works, supplies or services to be procured. The contracting authority asks in writing for the data and explanation underlying the price or costs, and notifies the other tenderers of the request in writing at the same time (Kbt. Section 72(1)). The Kbt. sets no numerical threshold for when a tender appears abnormally low: the contracting authority must judge that in relation to the subject-matter. The request for an explanation is part of the examination of tenders (bírálat) (Kbt. Section 69(2)).

In an open procedure, the contracting authority may provide in the procurement documents that it will examine abnormally low prices or costs and other disproportionate commitments after the evaluation, and only for the best-ranked tenderer, or for it and one or more of the next. If the tender examined proves invalid on that ground, the next tenderer in the ranking takes its place (Kbt. Section 81(4)).

Which explanations may be accepted

The contracting authority may take into account an objective explanation relating in particular to (Kbt. Section 72(2)):

  • the economics of the manufacturing process, of the construction method or of the method of providing the services;
  • the technical solution chosen;
  • exceptionally favourable conditions available to the tenderer for performing the contract;
  • the originality of the supplies, works or services offered;
  • compliance with environmental, social and labour law requirements;
  • the possibility of the tenderer obtaining State aid.

The list is not exhaustive («különösen», in particular), but the explanation must have an objective basis.

Supplementary explanation and comparison

Where it is doubtful whether the explanation is acceptable, the contracting authority may ask for a supplementary explanation, notifying the other tenderers at the same time. The tenderer is under a duty to give the contracting authority every fact, data and calculation on the soundness of its price, so that the contracting authority can decide after proper consideration (Kbt. Section 72(3)). Where needed for the decision, the contracting authority may also ask the other tenderers, for comparison, for the data underlying specified elements of their tenders (Kbt. Section 72(5)).

When the tender is invalid

The contracting authority must declare the tender invalid if the information provided does not adequately explain that the contract can be performed at that price or cost (Kbt. Section 72(3)). A tender is also invalid if it contains an abnormally low consideration or another condition that cannot be fulfilled, or if the tenderer has not adequately explained why the suspicion is unfounded (Kbt. Section 73(1)(e)).

An explanation is inadequate in particular where the price or cost is abnormally low because the tender does not comply with the environmental, social and labour law requirements laid down by law, by a collective agreement that must be applied, or by the international conventions listed in Annex 4 (Kbt. Section 72(4), Kbt. Section 73(1)(g), Kbt. Annex 4). To assess this, the contracting authority may also ask the tenderer for information on the guideline wages that must be applied in the sector (Kbt. Section 72(4)). The Public Procurement Authority (Közbeszerzési Hatóság) publishes on its website, on the basis of data the minister responsible for employment policy provides every year, information on the mandatory minimum wages that apply in particular sectors (Kbt. Section 73(2)); and the contracting authority gives in the procurement documents the names of the bodies from which information on these requirements may be obtained (Kbt. Section 73(3)).

State aid and foreign subsidies

The contracting authority may declare invalid a tender whose consideration it found abnormally low because of State aid only if it first asked the tenderer in writing for information and the tenderer could not prove that it obtained the aid lawfully. The contracting authority informs the European Commission, through the Public Procurement Authority, of tenders found invalid on this ground (Kbt. Section 72(6)).

Where the estimated value of the procurement reaches the value in Article 28(1)(a) of Regulation (EU) 2022/2560 on foreign subsidies distorting the internal market, and an abnormally low price or cost would have to be examined solely because of a possible foreign subsidy, the contracting authority proceeds as Article 29(7) of that Regulation provides (Kbt. Section 80/B(2)(c)).

Not only the price: other disproportionate commitments

The same procedure applies, with the necessary changes, where another element of the tender contains a commitment that is considered impossible to fulfil. The contracting authority then declares the tender invalid if the information provided does not adequately explain that the commitment can be fulfilled (Kbt. Section 72(7)).

Business secrets and access to documents

Documents containing business secrets may be placed separately in the explanation under Section 72, with detailed reasons (Kbt. Section 44(1)). The tenderer may not prohibit the disclosure of data that are evaluated, but it may prohibit the disclosure of the underlying partial information and base data, in particular the priced bill of quantities (Kbt. Section 44(3)). A tenderer that took part in the procedure may ask, within five days at most of the written summary (írásbeli összegezés) being sent, to inspect the part of another tenderer's explanation that contains no business secrets (Kbt. Section 45(1)).

A price that is too high is a different question

The Kbt. also deals with a price that is too high, but differently: the contracting authority may declare the procedure unsuccessful if the price in the best tender, or some of its components, show that concluding the contract would seriously breach the principle of efficient and responsible management of public funds (Kbt. Section 75(2)(h), Kbt. Section 2(4)). Before doing so it must, through a request for clarification, give the tenderer the opportunity to show that the price is proportionate, and it must set out the detailed reasons in the written summary (Kbt. Section 75(7)).

In practice

  • For contracting authorities: it is good practice to name in the request which price or cost elements appear abnormally low and which supporting data are expected, since the Kbt. requires a request for the data and explanation underlying the price or costs (Kbt. Section 72(1)).
  • It is worth recording the assessment in writing; the evaluation committee (bírálóbizottság) in any case prepares a written expert opinion and a proposal for the decision (Kbt. Section 27(4)).
  • For tenderers: make the reply itemised and verifiable; providing the facts, data and calculations is the tenderer's duty, and if the information does not show that the contract can be performed, the tender is invalid (Kbt. Section 72(3)).
  • The examination is part of the assessment of tenders, so it runs alongside the rules on missing documents and clarification; its outcome appears in the written summary, and the award criteria determine which commitments are evaluated.

Want your tender documents checked before publication? We will show you how Procurelex Ellenőrzés does it.

Request a demo

General information on the Kbt. in force. Not legal advice.