National regime: procurement below the EU thresholds

When Part Three of the Kbt. applies, which purchases below the EU thresholds are outside the Act, and which procedures a contracting authority may choose from (Sections 110 to 117).

Updated 17 November 2026Draft – awaiting legal review

Legal basisSection 110 · Section 111 · Section 112(1) · Section 114(1) · Section 114(2) · Section 114(4) · Section 114(5) · Section 115(1) · Section 115(2) · Section 116(1) · Section 117(2) · official text

Procurements below the EU thresholds that reach the national thresholds are governed by Part Three (Harmadik Rész) of the Kbt. (Sections 110 to 117), known in practice as the national regime (nemzeti eljárásrend). This guide explains when it applies, which purchases are outside the Act, which procedures a contracting authority may choose from, and how they differ from the EU regime.

When it applies

Part Three applies to procurements whose value is below the EU threshold and at the same time reaches the national threshold, works and services concessions excepted (Kbt. Section 110); concessions are governed by Part Four (Kbt. Section 118(1)). Part Three may also, or must, be applied where Chapter III of the Act allows or requires it (Kbt. Section 110): for small lots carved out of a procurement reaching the EU threshold (Kbt. Section 19(4)) and for the social and other specific services of Annex 3 (Kbt. Section 21(2)). A contracting authority also acts lawfully if it applies Part Two instead of Part Three (Kbt. Section 21(1)). The thresholds are in the guide on thresholds.

Exemptions below the EU threshold

Section 111 lists the purchases below the EU threshold to which the Kbt. does not apply (Kbt. Section 111). The more common ones:

  • school textbooks supplied through the school textbook system, if listed in the official textbook register (Kbt. Section 111(a));
  • certain services of Annex 3 – publicly funded health services within the duty to provide care, hotel and restaurant services, legal services and ancillary purchasing services (Kbt. Section 111(c)) – and any service of Annex 3 whose estimated value is under HUF 50 million (Kbt. Section 111(d));
  • certain foodstuffs, such as chilled food and cooking ingredients, fruit and vegetables, milk and dairy products, bread and bakery products, eggs (Kbt. Section 111(f));
  • the creation of a literary (professional, scientific) work, consultancy or personal interpreting needed for the contracting authority's core activity (Kbt. Section 111(g));
  • tickets and passes for passenger transport (Kbt. Section 111(h));
  • books, periodicals, electronic databases, cultural goods and musical instruments (Kbt. Section 111(n));
  • architectural and engineering, interior, urban planning and landscape design services for buildings (Kbt. Section 111(r));
  • supplies and services directly linked to research and development or innovation activities (Kbt. Section 111(v)).

These exemptions cannot be applied to small lots carved out under Section 19(4) (Kbt. Section 19(5)). The exemptions of Sections 9 to 14 apply whatever the value; they are covered in the guide on exemptions.

Two routes: own rules, or Part Two with derogations

At its choice, the contracting authority either conducts a procedure designed freely under Section 117, or follows the rules of Part Two with the derogations of Sections 114 to 116 (Kbt. Section 112(1)). For utilities contracts, Part Two is applied in accordance with the separate legislation as well (Kbt. Section 112(2)). Section 113 has been repealed; no procedure can be based on it.

On the second route the contracting authority chooses among the procedures of Section 49 (Kbt. Section 49(1)), described in the guide on procedure types. Since a procedure cannot be switched to another type once it has started (Kbt. Section 49(3)), it is good practice to make and document the choice while preparing the procurement.

The derogations of Sections 114 and 114/A

  • Exclusion grounds and selection. The contracting authority may apply one or more of the exclusion grounds of Sections 62 and 63, and must apply those of Section 62(1)(h) to (k) and (m) – false information, undue influence, grounds relating to tax residence and transparency, and distortion of competition arising from a conflict of interest; it need not, however, set selection criteria (Kbt. Section 114(1)).
  • Declaration and proof. The standard form of the European Single Procurement Document is not used: in the declaration of Section 67(1) the economic operator only states that the selection criteria are met, and submits the detailed data and the certificates when the contracting authority asks for them under Section 69 (Kbt. Section 114(2)). Except for services of Annex 3 reaching the EU threshold, the contracting authority may instead require the certificates to be submitted with the tender or the request to participate (Kbt. Section 114/A(1)).
  • Procurement documents. For works the procurement documents must be made available, except in certain negotiated procedures without prior publication; for supplies and services the essential contract terms may be given instead of a draft contract (Kbt. Section 114(3)).
  • Time limits. In open, restricted and negotiated procedures the time limit for tenders is at least ten days for supplies and services and at least fifteen days for works; in the participation stage, enough time must be given to apply properly (Kbt. Section 114(4)). Where a change to the procurement documents is not significant, the time limit need not be extended if the change is sent no later than the third day before the day the time limit expires, or, where a notice must be published, dispatched no later than the fifth day (Kbt. Section 114(4a)).
  • Procedure types. The negotiated procedure and the competitive dialogue may be used in any case (Kbt. Section 114(5)). A negotiated procedure without prior publication may also be used where publicly announced, exceptionally favourable conditions open to anyone are available only for a short time, the price is substantially below market prices, and those conditions would be lost if a Part Three procedure were followed; at least three economic operators must still be invited to tender (Kbt. Section 114(9), Kbt. Section 114(10)).
  • Reserved participation. Participation may be reserved for tenderers whose turnover in the previous year, net of VAT, was below HUF 100 million for supplies and services or HUF 1 billion for works, provided that their subcontractors and the entities whose capacity they rely on meet the same condition (Kbt. Section 114(11)); for works, only where the estimated value – calculated without aggregation – does not exceed HUF 500 million (Kbt. Section 114(12)).
  • Pre-litigation dispute resolution. A request for pre-litigation dispute resolution (előzetes vitarendezés) concerning the notice and the procurement documents may be made until the time limit for tenders or requests to participate expires (Kbt. Section 114(13)).
  • Exceeding the estimated value. If the contract with the winning tenderer would exceed the estimated value, and the rules applied to the procedure could not lawfully have been used for that value, the procedure must be declared unsuccessful (Kbt. Section 114(8)).

Works below HUF 300 million (Section 115)

Where the estimated value of works is below HUF 300 million and the procurement is not financed in whole or in part from EU funds, the contracting authority may also apply the national-regime rules of the open procedure or of the negotiated procedure without prior publication with the derogations of Section 115, provided it knows of enough economic operators able to perform the contract to ensure fair competition (Kbt. Section 115(1)). In that case:

  • instead of publishing a notice, it sends an invitation to tender in writing, directly and at the same time, to at least five economic operators; only operators able to perform and professionally reliable may be invited, the participation of micro, small and medium-sized enterprises must be ensured where possible, and the operators invited should be varied where possible (Kbt. Section 115(2));
  • no selection criteria may be set (Kbt. Section 115(2));
  • under the open procedure rules, the minimum time limit for tenders does not apply, and only the operators invited may tender: not jointly with one another, but jointly with an operator not invited (Kbt. Section 115(3), Kbt. Section 115(4));
  • the contracting authority need not request further missing documents (hiánypótlás) where they would be needed because of a document submitted, or an economic operator newly named, in response to an earlier request (Kbt. Section 115(6));
  • the invitation and the procurement documents must be published in the EKR (elektronikus közbeszerzési rendszer) when the procedure starts, and the names and addresses of the operators invited and the record of the opening of tenders without delay after the opening (Kbt. Section 115(7));
  • the standstill period is five days from sending the written summary (írásbeli összegezés) (Kbt. Section 131(6)), the ten-day bar on concluding the contract after a request for pre-litigation dispute resolution becomes five days as well (Kbt. Section 115(2)), and a request for review of the decision closing the procedure must be submitted within five days (Kbt. Section 148(4)).

Works of such value may also be procured in a procedure launched by a notice (Kbt. Section 115(1)).

Electronic bidding (Section 116)

For supplies the procedure may also be run as electronic bidding (elektronikus licit): an electronic auction held without tenders being submitted beforehand, applying the national-regime rules of the open procedure with derogations and the detailed rules of a government decree (Kbt. Section 116(1)). No selection criteria may be set, and variants must be excluded (Kbt. Section 116(2)); to take part, an economic operator submits a request for registration, which may not be made conditional on a bid security (Kbt. Section 116(3)).

Own procurement rules (Section 117)

The contracting authority may also design its own procedural rules, not bound by Part Two (Kbt. Section 117(1)). It must set them out in the contract notice, may not switch from the type of procedure it has chosen to another, and the notice must ensure that economic operators can tender on an equal footing (Kbt. Section 117(2)). The notice is published as a notice following the template set by separate legislation; it must give the main details of the contract, the award criteria and method, and the time limit for tenders (Kbt. Section 117(3)). Only exclusion grounds laid down in the Act may be applied, and those of Section 62(1)(h) to (k) and (m) must be (Kbt. Section 117(4)). Adequate publicity, the participation of economic operators established in the European Union, adequate time limits and a non-discriminatory technical specification must be ensured (Kbt. Section 117(5), Kbt. Section 117(6), Kbt. Section 117(7)). Those concerned must be informed in writing of every decision affecting the outcome no later than three working days after it is taken, and once the evaluation is complete a written summary must be sent to all tenderers (Kbt. Section 117(8)).

Want your tender documents checked before publication? We will show you how Procurelex Ellenőrzés does it.

Request a demo

General information on the Kbt. in force. Not legal advice.