When is a procurement required?

When the Kbt. requires a public procurement procedure: who must procure, the thresholds for 2026, how the estimated value is calculated, and which exemptions exist.

Updated 17 November 20269 questionsDraft – awaiting legal review

Whether a purchase must go through a public procurement procedure depends on three questions: is the buyer a contracting authority, does the estimated value of the purchase reach the threshold, and is there an exemption that applies to it. The answers above summarise the rules of the Kbt.; the guides cover them in detail.

The thresholds and the regimes are in the guide on thresholds, the calculation of the estimated value and aggregation in the guide on estimated value, procedures below the EU thresholds in the guide on the national regime, and the exemptions in the guide on exemptions. The thresholds, each with its legal basis, are also on the thresholds page.

When must a public procurement procedure be conducted?

When a contracting authority defined in Sections 5 to 7 concludes a public contract, works concession or services concession whose value reaches the thresholds of Section 15(1) (Kbt. Section 4(1)). A public contract is awarded through a public procurement procedure, a concession through a concession award procedure (Kbt. Section 4(2)).

Legal basisSection 4(1) · Section 4(2) · official text

Who must procure?

Contracting authorities (ajánlatkérők): among others ministries, the central purchasing body designated by the Government, the State, budgetary bodies and local self-governments, and bodies established for activities in the general interest that are not industrial or commercial, where another contracting authority, Parliament or the Government supervises them, finances them for the most part or appoints most of their managers (Kbt. Section 5(1)). Utility contracting authorities are defined in Sections 6 and 7 (Kbt. Section 6(1), Kbt. Section 7(1)). For certain subsidised purchases, other organisations may also have to conduct a procurement procedure (Kbt. Section 5(2), Kbt. Section 5(3)).

Legal basisSection 5(1) · Section 6(1) · Section 7(1) · Section 5(2) · Section 5(3) · official text

What are the national thresholds for 2026?

HUF 20 million for supplies and services, HUF 60 million for works, HUF 30 million for services concessions and HUF 100 million for works concessions; for utilities contracts, HUF 50 million for supplies and services, HUF 100 million for works and for services concessions, and HUF 200 million for works concessions. The national thresholds are set each year by the act on the central budget (Kbt. Section 15(3)); the 2026 values are in Section 75 of Act LXIX of 2025.

Legal basisSection 15(3) · official text

What are the EU thresholds?

From 1 January 2026 to 31 December 2027: EUR 5,404,000 for works and concessions; for supplies and services, EUR 140,000 for ministries and the central purchasing body designated by the Government and EUR 216,000 for other contracting authorities; EUR 750,000 for the services of Annex 3. The European Commission sets the EU thresholds (Kbt. Section 15(2)), and the Public Procurement Authority (Közbeszerzési Hatóság) publishes their forint amounts (Kbt. Section 15(5)). The forint amounts and the utilities values are in the guide on thresholds.

Legal basisSection 15(2) · Section 15(5) · official text

Which regime applies?

A procurement whose value reaches or exceeds the EU threshold follows Part Two of the Kbt. (the EU regime); one below the EU threshold that reaches the national threshold follows Part Three (the national regime) (Kbt. Section 21(1)). Services of Annex 3 follow Part Three (Kbt. Section 21(2)), and concessions Part Four (Kbt. Section 21(3)).

Legal basisSection 21(1) · Section 21(2) · Section 21(3) · official text

Is the value compared with the threshold net or gross?

Net: the estimated value is the total consideration, net of VAT, generally asked or offered on the market for the subject-matter, at the commencement of the procurement (Kbt. Section 16(1)). It includes the value of any optional part and, where a quantity range is set, the largest quantity stated in the contract (Kbt. Section 16(1)).

Legal basisSection 16(1) · official text

May a purchase be split so that it falls below the threshold?

No. A procurement must not be split in a way that leads to circumventing the Act or the rules for procurements reaching the EU thresholds (Kbt. Section 19(2)). Where works, services for the same immediate purpose, or supplies for identical or similar use are procured through several contracts, the value of the lots must be aggregated (Kbt. Section 19(3)).

Legal basisSection 19(2) · Section 19(3) · official text

Is a procurement procedure required below the national threshold?

Not under the Kbt.: the obligation to conduct a procurement procedure applies to contracts whose value reaches the thresholds (Kbt. Section 4(1)). Whether a purchase stays below the threshold depends on its aggregated estimated value (Kbt. Section 19(3)). An organisation that is not a contracting authority but undertakes a procedure under the Kbt. voluntarily or by contract, or is required to by law, must comply with the Act (Kbt. Section 5(4)).

Legal basisSection 4(1) · Section 19(3) · Section 5(4) · official text

Are there exemptions for purchases that reach the thresholds?

Yes. The exemptions of Sections 9 to 14 apply whatever the value, for example to in-house contracts (Kbt. Section 9(1)(h)) and to cooperation between contracting authorities (Kbt. Section 9(1)(j)); below the EU threshold Section 111 lists further exemptions (Kbt. Section 111). The guide on exemptions covers the details.

Legal basisSection 9(1)(h) · Section 9(1)(j) · Section 111 · official text

Want your tender documents checked before publication? We will show you how Procurelex Ellenőrzés does it.

Request a demo

General information on the Kbt. in force. Not legal advice.