# Subcontractors in public procurement

- URL: https://procurelex.hu/en/guides/subcontractors
- Updated 2026-11-17
- Draft – awaiting legal review
- Legal basis: Kbt. Section 3, point 2, Kbt. Section 66(6), Kbt. Section 67(4), Kbt. Section 36(1)(b), Kbt. Section 71(4), Kbt. Section 73(1)(c), Kbt. Section 138(2), Kbt. Section 138(3), Kbt. Section 138(4), Kbt. Section 43(2)(e), Kbt. Section 143(1)(b)

Who counts as a subcontractor under the Kbt., what must be said about subcontractors in the tender and when the contract is signed, what happens if one is subject to an exclusion ground, and what the contracting authority publishes about them.

The Kbt. has specific rules on subcontractors, from the tender to the performance of the contract. This guide explains who counts as a subcontractor, what the tender must say about them, what happens if one is subject to an exclusion ground, what the winning tenderer must notify during performance, and what data the contracting authority publishes.

## Who is a subcontractor

A [subcontractor](https://procurelex.hu/en/glossary/subcontractor) (alvállalkozó) is an economic operator that takes part directly, brought in by the tenderer, in performing a contract concluded as the result of a procurement procedure ([Kbt. Section 3, point 2](https://procurelex.hu/en/kbt/3#pp2)). The following are not subcontractors:

- an economic operator that carries out its activity on the basis of an exclusive right ([Kbt. Section 3, point 2(a)](https://procurelex.hu/en/kbt/3#pp2-a));
- a manufacturer, distributor, or seller of parts or raw materials to be used for performance ([Kbt. Section 3, point 2(b)](https://procurelex.hu/en/kbt/3#pp2-b));
- in works contracts, a seller of building materials ([Kbt. Section 3, point 2(c)](https://procurelex.hu/en/kbt/3#pp2-c)).

No one subject to an exclusion ground may be a subcontractor ([Kbt. Section 62(1)](https://procurelex.hu/en/kbt/62#p1)), nor – unless it is a listed company limited by shares (nyilvánosan működő részvénytársaság) – an organisation owned by one of the office-holders listed in Section 25(6) or by their relatives ([Kbt. Section 25(6)](https://procurelex.hu/en/kbt/25#p6)). In the same procedure – and, where tenders for lots are allowed, for the same lot – a tenderer may not be another tenderer's subcontractor ([Kbt. Section 36(1)(b)](https://procurelex.hu/en/kbt/36#p1-b)).

A subcontractor must be distinguished from an entity that lends its capacity to prove the tenderer's suitability (see the [guide to selection criteria](https://procurelex.hu/en/guides/selection-criteria)). The winning tenderer must involve such an entity in performance in line with its commitment ([Kbt. Section 138(2)](https://procurelex.hu/en/kbt/138#p2)), and for requirements on experts and references the entity must actually take part in performance ([Kbt. Section 65(9)](https://procurelex.hu/en/kbt/65#p9)).

## In the tender

- The contracting authority may require in the procurement documents that the tender (or request to participate) states the part or parts of the procurement for which the tenderer intends to use subcontractors, the subcontractors it intends to use for them that are already known when the tender is submitted, and the planned share of subcontracted work, as a percentage of the tenderer's performance ([Kbt. Section 66(6)](https://procurelex.hu/en/kbt/66#p6)).
- In every case the tenderer must declare that it will not use a subcontractor subject to the exclusion grounds of Section 62 – or of Section 63, where these apply – even if the authority did not ask for known subcontractors to be named ([Kbt. Section 67(4)](https://procurelex.hu/en/kbt/67#p4)).

## If a subcontractor is subject to an exclusion ground

The contracting authority must exclude from the procedure a subcontractor subject to an exclusion ground ([Kbt. Section 74(1)](https://procurelex.hu/en/kbt/74#p1)). If this comes to light for a named subcontractor, the authority excludes it and, in a request to remedy deficiencies (hiánypótlás), asks the tenderer to name another economic operator in its place where needed ([Kbt. Section 71(4)](https://procurelex.hu/en/kbt/71#p4)).

The tender is invalid, however, if the subcontractor was excluded under point i), j) or o) of Section 62(1) and the tenderer cannot prove that it did not know of the ground and, with due care, need not have known – and, for point o), also that the ground did not affect its tender ([Kbt. Section 73(1)(c)](https://procurelex.hu/en/kbt/73#p1-c)). The authority must give the tenderer the chance to prove this through a request for clarification (felvilágosítás) ([Kbt. Section 73(4)](https://procurelex.hu/en/kbt/73#p4)).

If a new operator named in a remedied tender would make a further request to remedy deficiencies necessary, the authority need not issue it, provided it said so in advance in the procurement documents ([Kbt. Section 71(6)](https://procurelex.hu/en/kbt/71#p6)).

## During performance of the contract

The contract must be performed by the winning tenderer – by the joint tenderers in a joint tender, or by a project company where one is required or allowed ([Kbt. Section 138(1)](https://procurelex.hu/en/kbt/138#p1)). The contracting authority may not restrict the tenderer's right to use subcontractors, unless it used the option of Section 65(10), that is, required certain critical tasks to be performed by the tenderer itself ([Kbt. Section 138(3)](https://procurelex.hu/en/kbt/138#p3), [Kbt. Section 65(10)](https://procurelex.hu/en/kbt/65#p10)).

The winning tenderer ([Kbt. Section 138(3)](https://procurelex.hu/en/kbt/138#p3)):

- notifies the contracting authority of every subcontractor taking part in performance when the contract is concluded and, for subcontractors brought in later, in advance during performance;
- gives in the notification the subcontractor's name, tax number, contact details and authorised representative, the expected share of subcontracted work as a percentage, and the value of the price under the subcontract;
- informs the authority during performance of any change in the notified data;
- after the subcontracted work is done, notifies the actual percentage, the date of payment and the amount paid;
- declares in the contract that it will not use a subcontractor subject to the exclusion grounds that applied in the procedure; no separate declaration or certificate need be submitted on this.

An entity that helped prove suitability, or an expert presented for that purpose, may be dropped or replaced only if the tenderer still meets the selection criteria it met with them – and, where the authority used those data to limit the number of participants, meets them in an equivalent way ([Kbt. Section 138(2)](https://procurelex.hu/en/kbt/138#p2)). If using an entity or an expert was decisive in the evaluation of tenders, it cannot be dropped: the entity may change only through a succession in which the new entity can be regarded as its successor in every respect taken into account in the evaluation, and the evaluated expert only with the authority's consent, for an expert at least equivalent in every respect taken into account in the evaluation ([Kbt. Section 138(4)](https://procurelex.hu/en/kbt/138#p4)). Where the winning tenderers set up a project company, the subcontractors named in the tender conclude their contracts with the project company ([Kbt. Section 140(1)](https://procurelex.hu/en/kbt/140#p1)).

## Publication

The contracting authority publishes in the EKR (elektronikus közbeszerzési rendszer, the electronic public procurement system) the subcontractor's name and tax number, the part of the procurement it is used for, the expected share of its work and the value of its price, within thirty days of the notification, and later the actual share, the date of payment and the amount paid, at the same time as the data on performance of the contract ([Kbt. Section 43(2)(e)](https://procurelex.hu/en/kbt/43#p2-e)). These data are public in the public interest, and their disclosure may not be refused on grounds of business secrecy ([Kbt. Section 43(3)](https://procurelex.hu/en/kbt/43#p3)).

## If the rules are not complied with

- The contracting authority may terminate or withdraw from the contract if the tenderer does not ensure compliance with Section 138 ([Kbt. Section 143(1)(b)](https://procurelex.hu/en/kbt/143#p1-b)).
- As an optional exclusion ground, the authority may provide in the notice that no operator may take part that, under an earlier public contract, failed to pay more than 10% of an invoice owed to its subcontractor although the authority had paid it on time, where a final court judgment established this within three years ([Kbt. Section 63(1)(d)](https://procurelex.hu/en/kbt/63#p1-d)); see the [guide to exclusion grounds](https://procurelex.hu/en/guides/exclusion-grounds).
- As a special anti-corruption condition of performance, the authority may also set requirements on the transparency and verifiability of subcontractors ([Kbt. Section 132(4)(f)](https://procurelex.hu/en/kbt/132#p4-f)).

## Below the EU thresholds

In a procedure under Part Three, the contracting authority may reserve participation for tenderers whose turnover in the previous year, net of VAT, was below one hundred million forints for supplies and services, or one billion forints for works; their subcontractors and the entities lending them capacity must then meet the same condition ([Kbt. Section 114(11)](https://procurelex.hu/en/kbt/114#p11)). For works this is possible only if the estimated value of the purchase, counted without aggregating the lots, does not exceed five hundred million forints ([Kbt. Section 114(12)](https://procurelex.hu/en/kbt/114#p12)).